The tool compares the pace the customer needs with the pace your process delivers. Takt time is takt = available time ÷ demand, the maximum time you may spend per unit. Enter the available time and the cycle time in the same unit, minutes, because the result is labelled min/unit. The status is "On pace" when cycle ≤ takt (a cycle exactly equal to takt still counts) and "Over takt — bottleneck" when the cycle is longer. The third figure is the capacity for one shift at your cycle time, capacity = available time ÷ cycle, rounded to whole units; compare it with the demand. All three inputs must be above zero, otherwise there is no result. Use net available time (shift length minus breaks, meetings and planned stops), and a cycle time measured on the real process.

Worked example

A shift has 450 minutes of available time and the customer wants 300 units. Takt time is 450 ÷ 300 = 1.50 min/unit. The station measured at 1.8 minutes per unit is slower than takt (1.8 > 1.5), so the status is "Over takt — bottleneck". Its capacity is 450 ÷ 1.8 = 250 units per shift, 50 units short of the 300 required. A cycle time of 1.2 minutes would give 375 units and the status "On pace".

Try this example →

Common mistakes

  • Using the full shift length as available time. Takt is based on the time you can actually produce, so take off breaks, meetings and planned maintenance before entering it.
  • Mixing units, such as available time in hours and cycle time in seconds. Both must be in minutes, otherwise the status and capacity are meaningless.
  • Entering the supply instead of the demand. The demand is what the customer takes in the period, not what you plan to make or what is in stock.
  • Treating "On pace" as proof the line is fine. It compares one station against takt; a line is only as fast as its slowest station, so compare every station, and leave room for downtime.
  • Entering a best-case cycle time. A cycle time measured once on a good day makes the status look better than a normal shift will deliver.

Sources

About this calculator

Takt time — from the German Taktzeit, meaning “pulse” or “beat” — is the maximum time allowed per unit to keep up with customer demand: available production time divided by demand over that period. Cycle time is the actual time your process takes to complete one unit, measured on the shop floor.

Comparing the two tells you whether a process is keeping pace: if cycle time is longer than takt time, that step is a bottleneck holding back the whole line; if it’s shorter, that station has spare capacity. Lean manufacturing practitioners, industrial engineers, and Six Sigma teams use this comparison — a core concept from the Toyota Production System — to balance production lines and spot where to focus improvement efforts. This calculator computes takt time from your available time and demand, then flags whether your actual cycle time keeps pace.