Asphalt Calculator

Enter the area dimensions, compacted thickness and density to get the asphalt tonnage.

How it is calculated

The tool works in metric units for one rectangle. Length and width are in metres (m), thickness is in centimetres (cm) and density is in tonnes per cubic metre (t/m³). Area is length × width in m². Volume is area × thickness ÷ 100 in m³; dividing by 100 turns centimetres into metres. Tonnage is volume × density. All four values must be above zero, thickness may not exceed 100 cm and density may not exceed 5 t/m³; outside those limits no result is shown. Use the compacted thickness of the finished layer and the compacted density of the mix, which your supplier can give. There is no allowance for waste, uneven sub-base or thicker joints, so split an irregular area into rectangles and add the results.

Worked example

A driveway is 25 m long and 4 m wide, to be laid 5 cm thick with a mix density of 2.4 t/m³. Area: 25 × 4 = 100.00 m². Thickness in metres: 5 ÷ 100 = 0.05 m, so volume = 100 × 0.05 = 5.00 m³. Tonnage: 5.00 × 2.4 = 12.00 t. You would order at least 12.00 t, and in practice a little more to cover waste and low spots in the base.

Try this example →

Common mistakes

  • Entering the thickness in millimetres or metres. The field is centimetres, so 5 means 5 cm; 50 would be ten times the material, and anything above 100 gives no result.
  • Entering the density in pounds per cubic foot, such as 145. The field is tonnes per cubic metre, so use a figure around 2.4; a value above 5 is rejected and shows no result.
  • Using the loose thickness instead of the compacted thickness. Hot mix compresses when rolled, so the figure must describe the finished layer.
  • Entering the dimensions in feet. Length and width are metres, so convert first.
  • Ordering exactly the calculated tonnage. The tool has no waste allowance, and an uneven base or edges will need more.

About this calculator

Asphalt is ordered by weight, not by area, because paving contractors buy hot-mix asphalt by the ton from the plant. This calculator gets you there in three steps: it multiplies your area's length by width (in metres) to get square metres, multiplies that by the compacted thickness (in centimetres) to get a volume, and then multiplies the volume by the mix's density to convert it into tonnage — since asphalt is typically priced and delivered by weight, not volume.

Compacted hot-mix asphalt density typically runs around 2.2–2.4 metric tons per cubic meter, varying with the specific aggregate and binder mix used, which is why this calculator lets you enter your own density figure (in t/m³, starting from 2.4) rather than assuming a single fixed value — your supplier or spec sheet will usually have the exact number for the mix you are using. If your figure is in pounds per cubic foot (roughly 140–150), divide it by about 62.4 to convert it to t/m³.

Driveway installers, parking lot contractors and road construction estimators use a calculation like this to order the right tonnage before a pour, avoiding the costly mistakes of running short mid-job or paying for asphalt that never gets used.