Overhead Rate Calculator

Enter total overhead and total direct costs to get the overhead rate.

Result

60.00%
$0.60

How it is calculated

Enter total overhead (indirect costs) for the period and the total of the allocation base, here called direct costs, for the same period. The tool divides: rate = overhead / direct costs. It shows the result twice: as a percentage (rate × 100) and as an amount per one unit of the base, written with a dollar sign.

Overhead cannot be negative and direct costs must be above zero, otherwise there is no result. The tool does not decide which base you should use. If you enter direct labour hours or machine hours instead of money, the percentage is not meaningful, and the second figure is an amount per hour even though it carries a dollar sign. To apply the rate, multiply it by the base of a particular job.

Worked example

A workshop has 90,000 of yearly overhead (rent, utilities, supervision) and 150,000 of direct costs. Rate: 90,000 / 150,000 = 0.60, so the overhead rate is 60.00%, or $0.60 for every $1 of direct cost. A job with 4,000 of direct cost should therefore carry 4,000 × 0.60 = 2,400 of overhead, giving a full cost of 6,400 before profit.

Try this example →

Common mistakes

  • Using different periods for the two inputs, such as annual overhead with quarterly direct costs. The rate would be four times too high.
  • Putting direct costs that already include overhead in the denominator. The base should hold only the direct items.
  • Applying a rate based on labour cost to a job measured in machine hours. The rate only works with the same base it was built from.
  • Leaving selling or administrative costs out of overhead when they are meant to be included. The rate then understates what a job should be priced at.
  • Treating the rate as profit or markup. It recovers indirect costs; a profit margin is added on top.

About this calculator

Overhead rate is total overhead ÷ total direct costs (the chosen allocation base, entered as a money amount) — commonly direct labor cost or direct material cost — expressing how much indirect cost (rent, utilities, supervision, equipment depreciation) should be layered onto each unit of direct cost when pricing a job or product.

Manufacturers and job-cost contractors use it to make sure quoted prices actually cover the indirect costs of running the shop, not just materials and labor, and cost accountants use the same rate to allocate overhead across products or departments for accurate product-line profitability reporting. Per-hour rates (per labor or machine hour) are not shown here; for those, divide overhead by the hours yourself.